Commercial Plumbing Takeoff: 120,000 SF Office Building

A technical demonstration examining typical drawing sets, Division 22 scopes, quantified materials, MCAA labor hours, and bid formulation for a representative 5-story commercial office facility.

At a glance

Project Overview: 120,000 SF Commercial Office Demonstration Takeoff

This illustrative takeoff demonstrates how a 5-story commercial office building (64 fixtures, core multi-stall restrooms, break rooms, drinking fountains, copper water distribution, and cast iron soil stacks) is methodically quantified from digital P-series drawings using CSI MasterFormat Division 22 and MCAA labor unit standards.

Confirm scope and assumptions against your project documents.
Demonstration Area120,000 SF
Model Fixture Count64 Fixtures
Calculated Labor1,940 MCAA Hrs
Benchmark Bid Value$784,500

1. Drawings & Documents Received

  • Plumbing Sheets (P-001 through P-502): P-001 Legend & Notes, P-101 Underground Sewer, P-201–205 Floor Plans, P-401 Riser Diagrams, P-501 Fixture Schedules.
  • Architectural Floor Plans (A-Series): Used to cross-check partition wall thicknesses and chase dimensions for in-wall toilet carriers.
  • Project Specifications: Division 22 05 00 (Common Work), 22 11 16 (Domestic Water Piping), 22 13 16 (Sanitary Waste and Vent Piping).

2. Scope of Work Quantified

System / ComponentMaterial SpecifiedTakeoff QuantityNotes
Domestic Cold Water (DCW)Type L Hard Drawn Copper (ProPress)1,840 Linear FeetRisers 2-1/2\" stepping down to 3/4\" fixture branches
Domestic Hot Water (DHW & Return)Type L Copper w/ Fiberglass Insulation1,210 Linear FeetComplete with Taco recirculation circulator pump
Sanitary DWV & StacksCast Iron No-Hub (CISPI 301)1,620 Linear FeetHeavy-duty 4-band stainless steel couplings
Atmospheric Vent StacksCast Iron / PVC Sch 40 blend980 Linear FeetVTR penetrations through TPO roofing membrane
Commercial Restroom FixturesVitreous China + Sensor Flushometers64 Fixture UnitsZurn wall carriers & Sloan ECOS sensor valves

3. Hypothetical Coordination and Alternate Review

Challenge: Congested 3rd Floor Ceiling Plenum

In this hypothetical scenario, a duct route conflicts with a gravity waste drop. The estimator would flag the conflict in an RFI and carry a documented allowance until the designer approves a route. No completed project or verified rework saving is represented.

Value Engineering: Viega ProPress vs Solder Sweat

An illustrative press-joint alternate could be compared with the specified soldered or brazed system. Assuming 180 fewer installation hours at $85 per hour gives a $15,300 labor difference. These are example inputs, not measured savings; include fitting prices, tooling, approvals, and project productivity before accepting an alternate.

4. Illustrative Benchmark Summary

This demonstration model illustrates how an organized bill of materials and MCAA labor unit rate calculation establishes a target direct job cost of approximately $784,500 ($6.54/SF), showing the structure of a sample cost model. It is not a quote or evidence of a completed client project. Actual project bids will vary based on regional prevailing wages, supplier trade discounts, and local building code amendments.